Project Number Campus Project Name Package Number Bid Package Title Bid Date Awarded To Document
00-05102.00 University Park 2016 Roof Fall Protection 4 Fall Protection System 01/05/2017 Diversified Fall Protection
08-93143.00 University Park West Campus Steam Plant Improvements 1 Stack Demolition 12/20/2016 Hamon Custodis
00-04724.00 University Park East Halls Phase 1B 11 - 100% CD Package Site Concrete 12/08/2016 Hawbaker
00-04724.00 University Park East Halls Phase 1B 27 - 100% CD Package Specialties 12/08/2016
00-04724.00 University Park East Halls Phase 1B 12 - 100% CD Package Concrete Foundations and Flatwork 12/08/2016
00-04724.00 University Park East Halls Phase 1B 28 - 100% CD Package Residential Equipment 12/08/2016
00-04724.00 University Park East Halls Phase 1B 13 - 100% CD Package Structural Steel 12/08/2016 Altoona Pipe & Steel
00-04724.00 University Park East Halls Phase 1B 29 - 100% CD Package Window Treatment 12/08/2016
00-04724.00 University Park East Halls Phase 1B 14 - 100% CD Package Masonry and Masonry Restoration 12/08/2016 Cost Masonry
00-04724.00 University Park East Halls Phase 1B 30 - 100% CD Package Final Cleaning 12/08/2016
00-04724.00 University Park East Halls Phase 1B 15 - 100% CD Package Glass & Glazing 12/08/2016 Nittany Building Specilaties
00-04724.00 University Park East Halls Phase 1B 31 - 100% CD Package Demolition 12/08/2016 Interior Specialists
00-04724.00 University Park East Halls Phase 1B 16 - 100% CD Package Dry Wall, EIFS, Plaster Repair & ACT 12/08/2016 JC Orr & Son, Inc.
00-04724.00 University Park East Halls Phase 1B 17 - 100% CD Package Rough Carpentry, Finish Carpentry & Millwork 12/08/2016
00-04724.00 University Park East Halls Phase 1B 18 - 100% CD Package Waterproofing, Air Barrier and Below Grade Insulation 12/08/2016 JC Orr & Son, Inc.
00-04724.00 University Park East Halls Phase 1B 19 - 100% CD Package Sealants 12/08/2016
00-04724.00 University Park East Halls Phase 1B 20 - 100% CD Package Roofing, Sheet Metal & Metal Composite Panels 12/08/2016 R.H. Marcon
00-04724.00 University Park East Halls Phase 1B 21 - 100% CD Package Fireproofing 12/08/2016 JC Orr & Son, Inc.
00-04724.00 University Park East Halls Phase 1B 22 - 100% CD Package Doors, Frames, Hardware 12/08/2016 HC Hood Co.
00-04724.00 University Park East Halls Phase 1B 23 - 100% CD Package Flooring 12/08/2016 Nittany Building Specialties & J.P. Phillips