00-05991.00 |
University Park |
University Park Water Reclamation Facility (WRF) Upgrades, Stages 3, 4, 5 |
3.4 |
Post Tension Concrete Tanks (Alternate Bid) |
11/20/2018 |
|
|
00-05991.00 |
University Park |
University Park Water Reclamation Facility (WRF) Upgrades, Stages 3, 4, 5 |
17.0 |
Instrumentation & Controls |
11/20/2018 |
|
|
00-05991.00 |
University Park |
University Park Water Reclamation Facility (WRF) Upgrades, Stages 3, 4, 5 |
4.0 |
Masonry |
11/20/2018 |
|
|
00-06168.00 |
University Park |
East Halls Phase 2A, 100%CD Package |
17 |
Rough Carpentry, Finish Carpentry, Millwork |
11/20/2018 |
Easley & Rivers |
|
00-05991.00 |
University Park |
University Park Water Reclamation Facility (WRF) Upgrades, Stages 3, 4, 5 |
5.0 |
Structural Steel and Miscellaneous Metals |
11/20/2018 |
G.M. McCrossin |
|
00-06168.00 |
University Park |
East Halls Phase 2A, 100%CD Package |
18 |
Waterproofing, Air Barrier, and Below Grade Panels |
11/20/2018 |
R H Marcon/Leonard S. Fiore |
|
00-05991.00 |
University Park |
University Park Water Reclamation Facility (WRF) Upgrades, Stages 3, 4, 5 |
7.0 |
Roofing |
11/20/2018 |
|
|
00-06168.00 |
University Park |
East Halls Phase 2A, 100%CD Package |
23 |
Flooring |
11/20/2018 |
Nittany Building Specialties |
|
00-05991.00 |
University Park |
University Park Water Reclamation Facility (WRF) Upgrades, Stages 3, 4, 5 |
8.0 |
Doors and Windows |
11/20/2018 |
|
|
00-06168.00 |
University Park |
East Halls Phase 2A, 100%CD Package |
03 |
Plumbing |
11/20/2018 |
Jay R. Reynolds |
|
00-06168.00 |
University Park |
East Halls Phase 2A, 100%CD Package |
24 |
Painting |
11/20/2018 |
Saints Painting/Trihanson |
|
00-05991.00 |
University Park |
University Park Water Reclamation Facility (WRF) Upgrades, Stages 3, 4, 5 |
8.1 |
Overhead Coiling Doors |
11/20/2018 |
Central PA Dock and Door |
|
00-06168.00 |
University Park |
East Halls Phase 2A, 100%CD Package |
04 |
Fire Protection |
11/20/2018 |
S A Comunale |
|
00-06168.00 |
University Park |
East Halls Phase 2A, 100%CD Package |
28 |
Residential Equipment |
11/20/2018 |
|
|
00-05991.00 |
University Park |
University Park Water Reclamation Facility (WRF) Upgrades, Stages 3, 4, 5 |
8.2 |
General Trades - Administration Building COMPLETE |
11/20/2018 |
|
|
00-06168.00 |
University Park |
East Halls Phase 2A, 100%CD Package |
05 |
Mechanical |
11/20/2018 |
The Farfield Company |
|
00-06168.00 |
University Park |
East Halls Phase 2A, 100%CD Package |
30 |
Final Cleaning |
11/20/2018 |
|
|
00-05991.00 |
University Park |
University Park Water Reclamation Facility (WRF) Upgrades, Stages 3, 4, 5 |
9.0 |
Painting & Coatings |
11/20/2018 |
|
|
00-06168.00 |
University Park |
East Halls Phase 2A, 100%CD Package |
06 |
Electrical |
11/20/2018 |
Bob Biter Electrical Enterprises |
|
00-06168.00 |
University Park |
East Halls Phase 2A, 100%CD Package |
31 |
Demolition |
11/20/2018 |
ISI |
|