General Construction
Bid Date / Prevailing Time:
Tuesday, April 25, 2017 - 3:00pm
Project:
Combined Heat and Power Plant
00-04925.00
Package Number:
B-06
Awarded To:
Premier Construction Group, Inc.
Additional Information:
General construction package B-06 includes supply & install of metal stud framing, drywall, finishes, waterproofing, fireproofing, frames/doors/hardware and some miscellaneous accessories.
Re-bid from July 27, 2016.